Plots 9 & 10 Newmarket

CI Industries 
CS2 Limited
Woods Hardwick
Bailey Johnson Hayes

£3.9m

 The design and build construction of 2 industrial units totalling some 58,000ft2, Plot 9, 23,000ft2 & Plot 10, 35,000ft2

Extensive ground modelling works were required to reduce the level of this site by up to 2.5m. Installation of a series of PCC retaining wall to the entire North and West boundaries were able to facilitate the construction of the 2 warehouses.

This is a brownfield development that required clearing and remediating to bring this former industrial storage site up to a suitable condition ready for construction works to commence.

This project is designed as a combination of composite and built up clad envelopes on steel frames on pad foundations with PFC and pre-cast concrete ground beams retaining flood poured ground bearing slabs. The building fabric - including windows, doors, glazing and fencing - all comply fully with Secure By Design requirements, as well as environmental improvements including diverse, native landscape planting, bird boxes, bat boxes, log piles and Lacewing habitat. The ground floor offices have high quality sophisticated lighting and heating controls, LED lighting, fire alarms, full air conditioning and mechanical ventilation, which all help to make this another prestigious build for our client.

The project also includes all associated external works and drainage, with bypass interceptors, storage crate water attenuation, leak detection, ducting installations for BT, an HV cable diversion, together with extensive new services to the site, LV power, gas, water, fire hydrant and BT.

The building complies fully with Secure by Design requirements, has achieved a BREEAM “Very Good” rating and was registered under the Considerate Constructors Scheme. 